Headquarters and Headquarter Company
November 3, 1969
Battalion Forward: 1-20 Infantry Headquarters is located at LZ Liz and continued their working with the ARVN units in their Area of Operations. TMF at 0252hrs detected movement northwest to southeast 7-8 persons engaged with artillery with unknown results. At 1000hrs Alpha Company 3-1 Infantry is located at BS735411 and continued to work the Area of Operations and at 1205hrs remain in their Day Logger. At 2000hrs Alpha Company 3-1 Infantry reports their locations 51 BS740398, 91 at BS739393, 96 BS734398, 01 at BS734398, and 06 BS740402.
Battalion Rear: Battalion Rear continued their Mission for providing general support for the Battalion.
Alpha Company
November 3, 1969
Alpha Company continued their Security Mission for the Land Clearing Operation. Alpha Company is at BS813482 working with joint operations with the ARVN and continued to use multiple patrolling and Day and Night ambushes in their Area of Operation. At 2000hrs Alpha Night Defense Position is at BS813482 with 06 at BS787407 and 55 personnel at BS786435.
Bravo Company
November 3, 1969
Bravo Company at their Day Logger at BS783433 is working joint operation with the ARVN forces using multiple patrolling and Day and Night ambushes in their Area of Operation. At 1157hrs Bravo Company 1-20 Infantry sent 20 Pax to Chu Lai for Stand Down, PZ 1152hrs and LZ 1230hrs. At 2000hrs Bravo Company Command Post, Recon and Rangers area at BS783433, 96 &172RF at BS771461, 01 & 147 RF BS789417, 169 PF BS787424, 95 & 215 PF BS778445, 93 & 216 PF BS776446, 94 BS781438, 05 BS783419, 54 BS786431. At 2230hrs 06 at BS787407 received a few small arms fire from 200 meters east of Night Defense Position returned fire with small arms with unknown results.
Charlie Company
November 3, 1969
Charlie Company conducts a Combat Assault with 1 Platoon PZ 0700hrs (BS728426) and LZ 0709hrs (BS761421) completed and cold. Charlie Company moved their Day Logger to BS728443. At 1555hrs Charlie Company request Dust Off of 1 Vietnamese civilian found wounded how she was wounded is unknown, Dust Off completed at 1616hrs.At 2000hrs Charlie Company is in their Night Defense Position at BS727441, 91 at LZ Liz and 01 at BS724439.
Delta Company
November 3, 1969
Delta Company will continue their Security Mission for LZ Liz.
Echo Company
November 3, 1969
Echo Company headquarters and 4.2 Mortar Platoon is location on LZ Liz, where the 4.2 Platoon providing direct fire support for the Battalion. Echo Company Headquarters has the responsibility for Base Defense. At 0900hrs Recon reports their location at BS783433 at 1600hrs Recon Platoon reports still in their OP. At 2000hrs Recon is with Bravo Company and Rangers located at BS783433.